A legacy miner becoming AI infrastructure
- The big idea is a pivot from Bitcoin mining to long-term AI and HPC data center leases.
- Management reported $819 million of liquidity as of August 2026.
- Keel has fully decommissioned all U.S. Bitcoin mining operations to focus on the infrastructure pivot.
- Keel claims its infrastructure assets represent a 2.2 GW power capacity pipeline.
- A permitting delay at the Panther Creek site highlights the execution risk of the transition.
The lease test
Keel is trying to turn old Bitcoin mining power sites into AI data centers. High-performance computing requires massive amounts of power for AI models and large workloads. If Keel signs long-term leases with giant cloud companies, the business could look more like a predictable infrastructure utility.
The bull case is clearer after the latest quarter. Liquidity surged to $819 million following a June convertible notes offering. This cash removes near-term financing concerns and fully funds the advancement of priority sites through lease execution.
The bear case is still real. Execution risk is high for complex engineering and regulatory rules. Final environmental permits for Panther Creek are taking months longer than originally expected. The key test is whether Keel can secure its targeted hyperscaler or neocloud leases by year-end 2026.
From hashpower to rent
Historically, Keel made most of its money from Bitcoin mining. It sold computing power to mining pools under Full Pay Per Share contracts. That cash is meant to help fund the AI data center pivot, but U.S. mining is now fully decommissioned as the transition speeds up.
The future model relies on developing and owning power generation and data centers to lease capacity under long-term contracts. While initially focused on triple-net leases, Keel may also structure leases on a modified gross basis to maintain operational control and meet faster customer demands.
The break point is timing. Mining cash is shrinking on purpose, while AI data center revenue is not expected to start until 2027. That leaves a period where the company is spending heavily before the new business proves itself.
What Keel is building
Legacy Bitcoin Mining
This is the remaining revenue base, but it is being aggressively wound down. All U.S. mining operations have been fully decommissioned.
Power and data center pipeline
Keel says its infrastructure assets represent a massive 2.2 GW power capacity pipeline to support future AI leases.
Near-term sites
Panther Creek, Sharon, and Moses Lake are the first three sites aimed at near-term AI infrastructure leases.
Sherbrooke HPC consolidation
Keel plans to consolidate 96 megawatts of legacy power agreements in Quebec into a single HPC and AI site.
Scrubgrass load study
Scrubgrass is an expansion option, with a detailed load study underway for an additional 750 MW.
Revenue is still North American mining
The mix below is based on continuing revenue by geography, as Keel does not yet report HPC revenue. It excludes discontinued Latin America operations.
What could break the pivot
No anchor leases
High impact · Medium oddsKeel needs large cloud or AI customers to sign long-term leases before the story changes. Without those contracts, the 2.2 GW pipeline is only potential. Missing the targeted leases by year-end 2026 would weaken the bull case.
Buildout and permitting delays
High impact · Medium oddsAI data centers need exact power, cooling, networking, and uptime standards. Final environmental permitting for Panther Creek is already taking months longer than expected. A delay can push revenue further out while costs keep running.
Cash burn before revenue
High impact · Medium oddsLiquidity risk is lower after a convertible note boosted capital to $819 million. Still, heavy operating losses remain during the transition period. If spending rises before leases are signed, the timeline gets tighter.
Power cost and regulation
Medium impact · Medium oddsBoth mining and AI data centers use a lot of electricity. Governments and regulators are paying more attention to energy use by data centers. Higher power costs would make leases harder to price.
In one breath
Is Keel still a Bitcoin miner?
Yes, but it is winding down fast. All U.S. mining is fully decommissioned, and the remaining operations exist mainly to generate cash for the AI pivot.
When could Keel start making money from AI data centers?
The internal view expects HPC infrastructure to be pre-revenue until 2027. The bigger near-term sign is signed long-term leases with large cloud or AI customers.
Why does liquidity matter so much for Keel?
Keel must spend money before the new data centers produce revenue. Total liquidity reached $819 million in August 2026, which removes near-term funding worries for its primary sites.
Sources and research notes
This page combines Finn's company research with public filings and other cited materials. The thesis is reviewed when material company information changes; Finn Scores use the latest available scoring data.
- Thesis reviewed
- September 6, 2026
- Score data
- September 27, 2026
- Reviewed by
- Shivam Bharuka
Comparable Financial - Capital Markets companies
Companies near Keel Infrastructure Corp. in Finn's Financial - Capital Markets industry ranking.

